TheoryLondon Waterloo is the biggest and busiest main line termini in the UK. It is owned by Network Rail. Bailey Rail was awarded the project for installation of the new Ticket Gating System.
Bailey Rail was appointed in February 2008 to provide the new Electrical, Mechanical and Telecommunications Services to New Automated Ticket Barrier Gateline including:-
Bailey Rail has achieved the key challenge of maintaining existing services, and minimising disruption to the millions of rail passengers that pass through Waterloo each day.
Bailey Rail have established a close working relationship with Network Rail’s gating Subcontractor ‘Cubic’ throughout to ensure seamless integration and a fully integrated detailed design with close liaison of all major players.
17/08/10
16/08/10
22/07/10
Network Rail
J Murphy and Sons Limited
Pell Frischmann
Pell Frischman / BPR
ICE
£1600,000
February 2008
A fully integrated multi system containment installed the whole length of the gateline in extremely limited available space.